Supplied summary

Brytemove Energy provided design, engineering, Engineer of Record (EOR), permitting management, and general contracting services across 100+ Southern California Edison (SCE) Charge Ready project sites.

The supplied case study is reproduced in full above. The original PDF is attached below for download.

Full case study

Reproduced from the supplied three-page SCE case study PDF.

SCE - Charge Ready ProgramExecution Framework for Utility-Administered DER Programs

Program
SCE Charge Ready
Summary
Funding and technical support to install EV charging infrastructure
Project types
CR: MFH, commercial, on-the-go. CR Transport: MD/HD private & public fleets. CR Pilot: DSA schools & public parks.

Over a five-year engagement encompassing 126 awarded projects, Brytemove Energy (BME) operated within Southern California Edison’s regulated Transportation Electrification program as a competitively selected technical execution contractor — performing standardized site assessment, engineering design, construction management, and integrated design-build services across a wide range of fleet and consumer charging sites.

This case study documents the delivery structure and formal procurement pathway under which BME was selected and retained within SCE’s regulated Transportation Electrification program.

A Public Procurement Pathway

SCE’s formal public RFP process established the governance, qualification standards, and performance expectations under which external technical contractors operated within the Charge Ready program. The competitive procurement framework defined scope boundaries, milestone controls, and reporting requirements consistent with regulated utility program oversight.

The contract structure also incorporated a two-year extension awarded on demonstrated performance, allowing scope continuity and expansion without re-procurement. The procurement structure included the following key elements:

  • Formal public RFP process with defined technical qualification criteria and evaluation standards
  • Utility-retained program management, including circuit capacity allocation, distribution system upgrades (make-ready), interconnection control, and overall program governance
  • Milestone-governed delivery framework aligned with utility distribution planning, circuit capacity provisioning, make-ready infrastructure sequencing, permitting, and construction controls

Earned Expansion: From Design Partner to Design-Build Delivery

The Charge Ready program was initially structured to separate design and construction scopes. Following demonstrated performance, SCE entrusted BME with integrated design-build delivery on select engagements. More than eighteen projects progressed under combined design-build — reflecting earned confidence within the utility’s oversight framework. This progression was not contracted at the outset; it was earned through consistent, disciplined execution.

Design and Engineering

Design and engineering activities were executed within SCE’s defined milestone structure and distribution planning framework. BME operated under standardized site assessment protocols, utility service feasibility review, and interconnection coordination requirements to ensure each project aligned with circuit capacity constraints and program delivery timelines.

The design workflow progressed through structured control points consistent with utility program governance:

  1. 01

    CD30-Conceptual

    Initial site assessment, rough layout, electrical service feasibility, preliminary load analysis.

  2. 02

    Utility Design-Base Map

    Above- and below-ground utility identification, civil validation, boundary or easement coordination.

  3. 03

    CD90-Detailed Design

    Stakeholder coordination, load study, new service planning, utility interconnection alignment.

  4. 04

    Permitting

    PE-stamped plan preparation, AHJ coordination, construction permit management.

  5. 05

    CD100-IFC

    Final construction drawings and field-ready documentation for deployment.

At peak program volume, this workflow supported more than 100 concurrent active sites across multiple Charge Ready segments while maintaining compliance with SCE’s milestone and reporting requirements.

Construction Management and General Contractor

When BME’s scope expanded to include construction services, delivery was performed within SCE’s regulated program controls and milestone structure. Acting as General Contractor, BME managed the full construction lifecycle in coordination with utility distribution planning, make-ready sequencing, and interconnection approval requirements.

  • Subcontractor Coordination

    Organized and managed electrical and civil subcontractors (union shops) aligned with project labor requirements.

  • Scheduling

    Developed and managed construction schedules coordinated with SCE milestone controls and site access constraints.

  • Deployment

    Managed on-site construction execution including electrical infrastructure, civil work, and equipment installation.

  • Completion & Closeout

    Completed final inspections, punch list resolution, system commissioning, and project closeout.

  • Documentation

    Compiled and submitted all as-built documentation, compliance records, and closeout packages per SCE requirements.

Construction execution was coordinated to align with utility capacity upgrades and energization timelines, ensuring distribution readiness prior to final system commissioning.

Institutional Capabilities Supporting Program Delivery

  • In-house PE-stamped electrical engineering enabling direct control of design quality, interconnection alignment, and permit issuance.
  • California C-10 Electrical Contractor licensing with statewide self-perform capabilities.
  • General Contractor (B) license supporting integrated design-build delivery within the regulated program structure.
  • Established labor and subcontractor network aligned with utility and project labor requirements.
  • Program management infrastructure capable of supporting 100+ concurrent active sites under milestone controls.

Source document

The complete case study is reproduced below from the supplied SCE case study PDF. The original three-page PDF is available to download.

Download the case study

Original case study · PDF · 3 pages · 1.6 MB
SCE Case Study Rev 5, supplied by Brytemove Media.